Project Description 
This projected construction program has an estimated construction budget of $36,760,000. The proposed scope of work includes the following potential elements:
  • Preconstruction and CMAR Services.
  • Improvements to elementary schools including the addition of a storm shelter.
  • Middle school additions and renovations. Parking lot and site improvements. Safety and security improvements.
  • High school additions and/or renovations. Safety and security improvements.
 
Evaluation Process
This request for statements of qualifications is the first phase of a three-phase qualifications-based selection process as required by K.S.A. 72-6760. The board will evaluate the qualifications of all firms in accordance with the instructions of the request for qualifications. The board will then prepare a short list containing a minimum of three and maximum of five qualified firms, which have the best and most relevant qualifications to perform the services required of the project, to participate in phase two of the selection process. If the board receives qualifications from less than four firms, all firms will be invited to participate in phase two of the selection process. The board will have discretion to disqualify any firm that, in the board’s opinion, lacks the minimal qualifications required to perform the work.
 
Prequalified firms selected in phase one will be invited as part of phase two to submit a proposal for construction management at-risk services. All prequalified firms shall submit proposed fees in a format required by the department of administration, including fees for preconstruction services, fees for general conditions, and fees for overhead and profits directly and only to the secretary of administration. The secretary of administration will score and rank the proposals for the best value and report such findings to the selection recommendation committee after all other interviews and scoring have been completed. The Kansas Secretary of Administration will score the CMaR fees. Those scores will be given to the selection committee after all other scoring has been completed. The fee scores shall then be added to the score matrix and final scores will then be calculated. The score on fees shall not account for more than 5% of the total possible score in this qualification based selection process.
 
Once all proposals have been submitted, the selection recommendation committee will interview as part of phase three each of the firms in executive session, allowing the competing firms to present their proposed team members, qualifications, project plan and to answer questions. The interview scoring will not account for more than 15% of the total possible score.
 
The selection recommendation committee will select the firm providing the best value based on the proposal criteria, weighting factors utilized to emphasize important elements of each project for approval by the board, and recommendation of the secretary of administration. All scoring criteria and weighting factors will be identified by the board in the request for proposal’s instructions to firms. The selection recommendation committee will proceed to negotiate with an attempt to enter into a contract with the firm receiving the best total score to serve as the construction manager at-risk for the project. Should the selection recommendation committee be unable to negotiate a satisfactory contract with the firm scoring the best total score, negotiations with that firm will be terminated, and the committee will undertake negotiations with the firm with the next best total score.
 
If the selection recommendation committee determines that it is not in the best interest of the board to proceed with the project pursuant to the proposals offered, the selection recommendation committee may reject all proposals. If all proposals are rejected, the board may solicit new proposals using different design criteria, budget constraints or qualifications.
 
The construction management at-risk contract for a project shall be prepared by the board and entered into between the board and the firm performing such construction management at-risk services. A construction management at-risk contract utilizing a cost plus guaranteed maximum price contract value shall return all savings under the guaranteed maximum price to the school district.
 
Subcontractor/Supplier Bidding Requirements
The board or the construction manager at-risk, at the board's discretion, will publish a construction services bid notice in the official newspaper of the school district and website of a statewide school board association or construction industry association, and in such other appropriate manner for the construction manager or general contractor as may be determined by the board. Each construction services bid notice will include the request for bids and other bidding information prepared by the construction manager at-risk and the board. The board may allow the construction manager at-risk to self-perform construction services provided the firm submits a sealed bid proposal under the same conditions as all other competing firms. At the time for opening the bids, the construction manager at-risk will evaluate the bids and determine the lowest responsible bidder except in the case of self-performed work for which the board shall determine the lowest responsible bidder. The construction manager at-risk shall enter into a contract with each firm performing the construction services for the project and make a public announcement of each firm selected at the first school board meeting following the selection.
 
Project Timetable
Advertise for CMAR Discussion to take place on 5/1/18: Tuesday, May 1, 2018
CMAR discussion during Board of Education Meeting: Wednesday, May 16, 2018
Advertise for Statement of Qualifications: Monday, May 21, 2018 – 6/4/18
Formally Issue Statement of Qualifications: Monday, June 4, 2018
Statement of Qualifications Due: Wednesday, June 13, 2018 (5 pm)
Bond Issue Election: Friday, June 15, 2018
Short List Announced by District: Monday, June 18, 2018
Formally Issue Requests for Proposals: Monday, June 18, 2018
Requests for Proposals Due: Monday, June 25, 2018 (5 pm)
Cost Proposal Form Due to Secretary of Administration: Monday, June 25, 2018 (5 pm)
Interviews: Wednesday, June 27, 2018
Board Consideration of Recommendation: Wednesday, July 18, 2018
 
Phase One Submission Requirements
The response to this request for statements of qualification must include the following information, at a minimum, and be organized as set out in the following outline:
 
  1. Firm Information: Provide the firm’s legal name and address of principal office(s);
  2. Management Approach: Description of the firm’s management approach, including experience working in and adjacent to operating schools;
  3. Relevant Experience: Experience in successfully completing relevant K-12 education projects (refer to Scope of Work above);
  4. CMAR Experience: Experience with providing construction management at-risk services, with emphasis on construction management at-risk services for Kansas Unified School Districts since the legalization of construction management at-risk for public projects in July 2008*;
  5. References: References from design professionals and owners from completed projects;
  6. Financial/Bonding: Financial statement and evidence of current bonding capacity in accordance with K.S.A. 60-1111 in an amount at least equal to the proposed construction budget of $36,760,000.
  7. Local Business Utilization: Plan to work with local subcontractors, vendors and businesses;
  8. Other Information: Any other information that may be relevant to evaluating such Statement of Qualifications.
*The District is most interested in evaluating each firm’s construction management at-risk experience on previous Kansas Unified School District projects. Projects delivered via other delivery methods (e.g. Construction Management-Agency, Design-Build, General Construction), or for non-Kansas Unified School District clients, will be considered less relevant by the District.
 
Instructions for Submitting a Response
Please deliver one original and 7 copies of your firm’s response to:
 
Dr. Mike Roth
Superintendent of Schools
Leavenworth USD 453
200 N. 4th Street
Leavenworth, KS 66048
 
Submission Deadline: Wednesday, June 13, 2018 at 5:00 PM CDT
 
Questions regarding this request may be directed to:
Dr. Mike Roth